Friday, November 20, 2015

Parting Shots ...

This is the 100th and final post for this blog. All the equipment has left and the jetty is once again under the firm control of the gulls, cormorants, and other wildlife. It didn't take them long to settle into their perch on new navigational signal.


The photo below was taken at the beginning of the construction just after the large CAT excavator was assembled. I opted not to posted then in an effort to avoid encouraging other people to wander around the construction site. At the time, the site had not completely fenced in.


I hope you have enjoyed following this blog as much I have enjoyed the experience of documenting this monumental project.

Tuesday, November 17, 2015

North Jetty Before & After

North Jetty BEFORE Repairs


This was original navigational aid light at the end of the jetty.


The small groin extending form the jetty was in poor shape


North Jetty at high tide as seen from Plum Island. You can see big gaps in the top of the jetty.

North Jetty AFTER Repairs



Mother Nature puts the newly repaired jetty to the test with some rough waves.

 


The repaired jetty handles the rough surf well.



The repaired groin



Repaired jetty as seen from Plum Island at high tide.


Friday, November 13, 2015

Assembling the New Navigational Light

DAY 1 Bringing Out the Poles

The job of setting up the new navigational light at the tip of the north jetty was the responsibility of the U.S. Coast Guard. The first day, coast guard members carried the metal poles for the structure of light out to the tip of the jetty. They seem unfazed by the waves crashing against the jetty and sending spray over them.


Two man job!


A little way action, no problem!


The concrete based was embedded into the tip of the jetty.

 

Returning from bringing out the poles.

DAY 2 - Assembling the Light

The team from US Coast Guard returned on another day to complete the assembly.  The four corner posts were setup and then the cross members attached. Red triangular panels were added and light installed.




DAY 3 - Installing the Battery

Two coast guard members returned on another day to install the battery which powers the light.


 

Wednesday, November 11, 2015

Tugs Waiting Out the Storm & Preparing to Leave

To ride out the forecasted hurricane, the tugs went to the Newburyport harbor side of the Merrimack River. The white tug was tied up to a mooring and the blue tug tide up to the dock. This proved to be a rare opportunity to get some up close photos og the tugboats.







Preparing to Leave


After the hurricane went out to see, the tugboats were placed on top of one of the crane barges and preparing to leave.





Tuesday, November 10, 2015

Equipment Waiting to Leave

A few photos of the equipment in various stages of waiting to leave the construction site.


A roll of cable and a claw for one of the excavators on a flatbed being prepared to leave.


The excavator claws took quite a beating on this project.


 This is what they looked like at the beginning - brand new with no scratches, rust, or wear & tear.


The wear and tear and already noticeable a couple days into the project.


One of the boats loaded onto a trailer.


two of excavators pulled up by the concrete seawall waiting to be loaded on trailers to leave.

Friday, November 6, 2015

Tracked Dump Truck Leaving

The fun runabout tracked dump truck was packed up and left on a flatbed truck. I managed to get a video of it leaving the parking lot Salisbury Beach State Reservation.


Short video of tracked dump truck leaving.


Wednesday, November 4, 2015

Disassembling the Large Excavator

The huge CAT 390F excavator arrived brand new on site in the late spring. It was trucked in different pieces on multiple flatbed trucks. It had to be disassembled to leave the site. By the time I had arrived, it was already partially taken part. I got photos of the arm and the counter weight being lifted onto a flatbed by the excavator itself. When it was originally assembled they used a wrecker truck crane to move the various parts.


The arm of excavator rests on the flatbed truck.


The counter-weight on the back of the excavator has been lowered to the ground (just visible on the right)


The back of the excavator without the counter-weight.


Preparing to pickup the counter-weight


Close-up of lift straps


As you can see the flatbed truck was moved and repositioned so the counter-weight could loaded.


Signaling the excavator operator.





Flatbed truck leaving


Short video of truck leaving.



Hooray, they are finally leaving!!!

Monday, November 2, 2015

Final Work on the South Jetty

The Army Corp was apparently unsatisfied with the additional work on the tip of the South Jetty which is on the Plum Island side of the mouth of the Merrimack River. Additional stone was added to the tip by one of the cranes still on site. By this point the blue and white tug boats had been taken out of the water and loaded onto a crane barge. A different tug, presumably the one sent to move the crane barges from the river to their next destination was used to maneuver the barge for this work. The stones had been loaded directly onto the deck of the crane barge.


A short video of the crane placing stones on the tip of the South Jetty.



North Jetty is on the left, South Jetty on the right.


Another tug was used for this project because the other two had already been taken out of the water.


crane swings around ...


Grabs a stone off the deck of the barge ...


Close-up of the grapple grabbing a stone


Swings the stone over to the South Jetty